A long-awaited natural gas-to-power project in Mozambique is expected to get under way again soon following a decision to renegotiate the financing.
Renewable power specialist Globeleq reports that it is in talks with project partners, including the International Finance Corporation, the OPEC Fund for International Development and the US International Development Finance Corporation, to revise the US$660 million deal, according to reports in Engineering News and CNBC Africa.
Just In: Globeleq in talks with investors to restructure Mozambique gas project https://t.co/i9gPlEwJpd https://t.co/xWU7LEzkdc
— Club of Mozambique (@clubOmozambique) November 11, 2026
The Mozambique government has also reportedly agreed to additional financial measures to support the project, including tariff adjustments.
The 450 MW Temane gas project is now expected to come on stream in 2028, to supply electicity to more than 800 000 customers. A potential phase 2, which will double capacity, will be considered once the plant is operational.
The project has been delayed because of cyclones and flooding as well as post-election violence in Mozambique’s Inhambane province, where the project is located.
Globeleq says the project will provide power to state utility Electricidade de Moçambique under a 25-year tolling agreement. The gas will be supplied from Sasol’s Pande and Temane fields.
The project also involves a 563 km transmission line to connect Mozambique’s northern, central and southern electricity networks.